Bond Work Completed at Green Elementary & Jim Hill High
September 3, 2019
Green Elementary School Parking Lot |
Jackson Public Schools has recently completed construction of a new parking lot at Green Elementary School and parking lot improvements at Jim Hill High School as part of the 2018 JPS Bond Construction Program. The parking lot work completed at Green Elementary involved converting an unused basketball court to a 27-space parking lot. The project was completed by R & L Unlimited, Inc. in August 2019.
Jim Hill High School Parking Lot |
At Jim Hill, Phase I of planned parking lot improvements were completed. The project involved pothole repairs in the most damaged areas. Phase II of this project will be completed in the summer of 2020. It will include a new concrete pad for the cafeteria loading dock area and resurfacing other damaged areas. Phase I parking lot improvement work was completed by R & L Unlimited, Inc. in August 2019.